10 USC 4272: Independent technical risk assessments
Result 1 of 1
   
 
10 USC 4272: Independent technical risk assessments Text contains those laws in effect on December 24, 2024
From Title 10-ARMED FORCESSubtitle A-General Military LawPART V-ACQUISITIONSubpart F-Major Systems, Major Defense Acquisition Programs, and Weapon Systems DevelopmentCHAPTER 322-MAJOR SYSTEMS AND MAJOR DEFENSE ACQUISITION PROGRAMS GENERALLYSUBCHAPTER IV-ADDITIONAL PROVISIONS APPLICABLE SPECIFICALLY TO MAJOR DEFENSE ACQUISITION PROGRAMS

§4272. Independent technical risk assessments

(a) In General.-With respect to a major defense acquisition program, the Secretary of Defense shall conduct or approve independent technical risk assessments-

(1) before any decision to grant Milestone A approval for the program pursuant to section 4251 of this title, that identifies critical technologies and manufacturing processes that need to be matured; and

(2) before any decision to grant Milestone B approval for the program pursuant to section 4252 of this title, any decision to enter into low-rate initial production or full-rate production, or at any other time considered appropriate by the Secretary, that includes the identification of any critical technologies or manufacturing processes that have not been successfully demonstrated in a relevant environment.


(b) Guidance.-The Secretary shall issue guidance and a framework for the conduct, execution, and approval of independent technical risk assessments.

(Added Pub. L. 114–328, div. A, title VIII, §807(a)(1), Dec. 23, 2016, 130 Stat. 2261 , §2448b; amended Pub. L. 116–92, div. A, title IX, §902(73), Dec. 20, 2019, 133 Stat. 1552 ; renumbered §4272 and amended Pub. L. 116–283, div. A, title XVIII, §1847(e)(2), Jan. 1, 2021, 134 Stat. 4256 .)


Editorial Notes

Amendments

2021-Pub. L. 116–283, §1847(e)(2), renumbered section 2448b of this title as this section.

Subsec. (a)(1). Pub. L. 116–283, §1847(e)(2)(A), substituted "section 4251" for "section 2366a".

Subsec. (a)(2). Pub. L. 116–283, §1847(e)(2)(B), substituted "section 4252" for "section 2366b".

2019-Pub. L. 116–92 added subsecs. (a) and (b) and struck out former subsecs. (a) and (b) which read as follows:

"(a) In General.-With respect to a major defense acquisition program, the Secretary of Defense shall ensure that an independent technical risk assessment is conducted-

"(1) before any decision to grant Milestone A approval for the program pursuant to section 2366a of this title, that identifies critical technologies and manufacturing processes that need to be matured; and

"(2) before any decision to grant Milestone B approval for the program pursuant to section 2366b of this title, any decision to enter into low-rate initial production or full-rate production, or at any other time considered appropriate by the Secretary, that includes the identification of any critical technologies or manufacturing processes that have not been successfully demonstrated in a relevant environment.

"(b) Categorization of Technical Risk Levels.-The Secretary shall issue guidance and a framework for categorizing the degree of technical and manufacturing risk in a major defense acquisition program."


Statutory Notes and Related Subsidiaries

Effective Date of 2021 Amendment

Amendment by Pub. L. 116–283 effective Jan. 1, 2022, with additional provisions for delayed implementation and applicability of existing law, see section 1801(d) of Pub. L. 116–283, set out as a note preceding section 3001 of this title.

Effective Date

Section applicable with respect to major defense acquisition programs that reach Milestone A after Oct. 1, 2017, see section 807(a)(2) of Pub. L. 114–328, set out as a note under section 4271 of this title.